The 3 month maintenance actions, listed below, may be performed by a trained projectionist who is familiar with potential hazards associated with the product. |
|
No. |
Maintenance action |
Remarks |
|---|---|---|
|
1 |
Clean the air vents/inlets of the projector:
|
Use a vacuum cleaner. |
|
2 |
Clean the cabinet of the projector. |
Removal overall dust accumulation on projector covers. |
|
3 |
Level verification of the liquid cooling circuit. |